Search
Logo
Construction Claims and Risk Management
Home
Archives
Archives

Past Articles

Explore past articles and analysis

Case Summaries

Key case summaries and rulings

Past Issues

Browse previous newsletter issues

AI Basics

AI Tasks & Agents To Manage Risks

About
Store
Subscribe
Login
Construction Contract & Claims Management

Upcoming Live Events

9-Part Construction Claims Series
Includes 2026 ASCE 4th Edition Claims Book
Starts October 14, 2026


Pay-if-Paid and Pay-when-Paid Construction Clauses:
Who Bears the Risk of Non-Payment?
October 21, 2026


Certified Payroll / Davis-Bacon Series
Now features California Public Works Law and Davis-Bacon Related Acts
Starts October 29, 2026


CPM Schedule Training 2-Part Series
Includes 2025 Wiley CPM Book
Starts November 10, 2026


Implied Obligations in Construction Contracts:
What You Don’t Know Can Hurt You
November 17, 2026


Construction Scheduling: Games People Play - 2-part Series
Starts December 10, 2026

Aug 31, 2026

•

1 min read


VOLUME 24   ISSUE 16   August 31, 2026

Editor's Notes

Project owners, public and private, favor prompt notification requirements for claims. This provides them with a tactical advantage. Contractors must give written notice of a specific claim quickly after the claim arises, or the claim is barred as untimely. The contractor loses all its claim rights. However, this device also poses problems for project owners.

A recent appellate court opinion criticized these quick-claim mandates. Depending on how the claim notice requirement is structured, the contractor may be forced to give notice while negotiations of the matter are still underway. Transforming fruitful negotiation into a costly, adversarial contest may not benefit either party.

The second case in this issue involves a contractor’s reliance on owner-furnished, as-built drawings. The contract said the drawings were approximate, not for construction purposes, and were provided merely as a courtesy. Did the owner effectively shift the risk of undisclosed site conditions to the contractor?

Case Summaries

Negotiation of Liquidated Damages Did Not Trigger Claim Notice Period

Ongoing negotiations of responsibility for an extended performance period did not establish a contractor’s knowledge of the basis for a claim. These negotiations did not trigger the 30-day claim notice period.

Read the Case Summary

Contractor Could Rely on As-Builts despite Contractual Disclaimers

Broad disclaimers did not negate the government's responsibility for the accuracy of the as-built drawings furnished to the contractor. The contractor’s notification of differing site conditions two weeks after discovery was sufficiently prompt.

Read the Case Summary

AI Applications in Claims & Risk

View Recent Articles
arrow-up-right

Owner’s Corner

View Recent Articles
arrow-up-right

Advisor Case Summaries

View Archives
arrow-up-right

Keep Reading

View more
caret-right

Subscribe to Our Newsletter

The latest news, articles, and resources, sent to your inbox weekly.

WPL Publishing Co., Inc.
7051 Rockledge Drive #1115, Bethesda, MD 20817