Search
Logo
Construction Claims and Risk Management
Home
Explore
Explore

Past Issues

Browse previous newsletter issues

Case Summaries

Key case summaries and rulings

Practical Guidance

Risk assessment for contractors and construction managers

AI Basics

AI Tasks & Agents To Manage Risks

Owner's Corner

Explore past articles

Subscribe
About
Login
Construction Contract & Claims Management

Upcoming Live Events

9-Part Construction Claims Series
Includes 2026 ASCE 4th Edition Claims Book
Continues October 28, 2026


Pay-if-Paid and Pay-when-Paid Construction Clauses:
Who Bears the Risk of Non-Payment?
October 21, 2026


Certified Payroll / Davis-Bacon Series
Now features California Public Works Law and Davis-Bacon Related Acts
Starts October 29, 2026


CPM Schedule Training 2-Part Series
Includes 2025 Wiley CPM Book
Starts November 10, 2026


Implied Obligations in Construction Contracts:
What You Don’t Know Can Hurt You
November 17, 2026


Construction Scheduling: Games People Play - 2-part Series
Starts December 10, 2026

Aug 31, 2026

•

2 min read


Contractor Could Rely on As-Builts Despite Contractual Disclaimers

Armed Services Board of Contract Appeals

Appeal of PDO Ahusaka Joint Venture LLC

Case no.: ASBCA No. 64490
Date filed: July 23, 2026

Overview

The Armed Services Board of Contract Appeals has ruled that a contractor could rely on the government’s as-built drawings despite broad disclaimers such as “approximate” and “not for construction.” Additionally, the contractor’s notification of the site conditions two weeks after discovery was considered prompt.

Background

The US Army awarded a fixed-price contract to PDO Ahusaka Joint Venture LLC to design and construct a storm system and flood control project at the US Army Garrison Detroit Arsenal in Warren, Michigan. The Army provided PDO with as-built drawings of buried utilities in the work area, as required by the contract.

The contract contained a number of statements qualifying the information in the as-built drawings. Locations were approximate and did not purport to be exact. The drawings were provided as a courtesy and were not to be relied upon for construction purposes.

The contract also placed responsibility with PDO regarding existing underground utilities. The contractor had to field-verify locations using ground-penetrating radar, have utilities mark existing lines, and obtain an excavation permit. PDO complied with these requirements. Nonetheless, PDO’s subcontractor encountered three unexpected, unidentified subsurface junction boxes while excavating the site.

PDO did not immediately notify the Army of this occurrence. The base fire department started experiencing disruptions to its emergency communication services. More than two weeks after striking the junction boxes, PDO informed the Army representative of the situation.

PDO subsequently filed a certified claim for a differing site condition. The Army denied the claim. The Army had not made affirmative representations regarding the location of all buried utilities and had expressly disclaimed responsibility for the information it furnished. The contractor's reliance on the as-built drawings was not reasonable. Also, PDO had failed to “promptly notify” the Army of the situation, as required by the differing site conditions clause. PDO appealed the denial of its claim.

The Ruling

The board said that when the Army furnished bidders with as-built drawings of subsurface utilities, the Army made affirmative representations regarding site conditions. The question was whether PDO was entitled to rely on those representations. Did the disclaimers shift the risk of differing site conditions back to the contractor?

“The Army asserts that these disclaimers made it unreasonable for PDO to rely on the contract’s representations as to underground utility locations. . . . However, such broad disclaimers of liability for changed conditions do not shift the risk from the government to the contractor. . . . Indeed, government disclaimers of responsibility for specifications which it authors are disdained by the courts.”

With regard to timely notice, the board noted that the differing site conditions clause does not define “promptly notify.” There is no bright line test. Timeliness is situational and judged on a case-by-case basis.

“PDO’s notice was still prompt despite the two-week delay; we have found ‘prompt’ notice even 21 months later, for example. . . . Even if not prompt, the Army has failed to establish how it was prejudiced. Untimely notice prejudices the government where it prevents the government from verifying the contractor’s differing site condition claim and weighing in on how the contractor should remedy the problem. . . . Here, the Army examined the site condition and directed PDO how to remediate, which undermines any assertion of prejudice.”

Conclusion

Notice timeliness always comes down to the issue of prejudice. If the contractor disturbs the actual conditions at the site before notifying the government, it may limit or preclude the government’s options for addressing those conditions. The contractor, not the government, will pay for any resulting increased costs.

Practical Takeaway

A contractor should be as prompt as reasonably possible in notifying the government of a site condition issue. This will mitigate the contractor’s liability exposure for increased performance costs.

Case Details

Participants:
For the government: Dana J. Chase
Before: Administrative Judge Daniel S. Herzfeld
Opinion by: Administrative Judge Herzfeld
Outcome: Appeal sustained regarding junction boxes

Source: Please click here to read the complete opinion.

Keep Reading

View more
caret-right

Subscribe to Our Newsletter

The latest news, articles, and resources, sent to your inbox weekly.

WPL Publishing Co., Inc.
PO Box 34215, Bethesda, MD 20827