Search
Logo
Construction Claims and Risk Management
Home
Explore
Explore

Past Issues

Browse previous newsletter issues

Case Summaries

Key case summaries and rulings

Practical Guidance

Risk assessment for contractors and construction managers

AI Basics

AI Tasks & Agents To Manage Risks

Owner's Corner

Explore past articles

Subscribe
About
Login
Construction Contract & Claims Management

Upcoming Live Events

9-Part Construction Claims Series
Includes 2026 ASCE 4th Edition Claims Book
Continues October 28, 2026


Pay-if-Paid and Pay-when-Paid Construction Clauses:
Who Bears the Risk of Non-Payment?
October 21, 2026


Certified Payroll / Davis-Bacon Series
Now features California Public Works Law and Davis-Bacon Related Acts
Starts October 29, 2026


CPM Schedule Training 2-Part Series
Includes 2025 Wiley CPM Book
Starts November 10, 2026


Implied Obligations in Construction Contracts:
What You Don’t Know Can Hurt You
November 17, 2026


Construction Scheduling: Games People Play - 2-part Series
Starts December 10, 2026

Jun 1, 2026

•

2 min read


Contract Accidentally Signed “Individually”

Appeals Court of Massachusetts

Costa Brothers Masonry, Inc. v. Town of Hingham

Case no. : 25-P-1021
Date filed: May 15, 2026

Overview

A Massachusetts appellate court has said that filed sub-bids for trade work on public projects must be based on sections of the contract specifications. Those specifications may reference drawings that require additional out-of-trade work.

Background

The town of Hingham was planning to build a public safety facility. In accordance with the Massachusetts filed sub-bid statute, G. L. c. 149, section 44F, the town solicited bids for various categories of trade work. Costa Brothers Masonry Inc. submitted the low masonry bid. Colantonio, Inc., the low bidder on the general contract, entered into a masonry subcontract with Costa for $2,417,000. The subcontract incorporated the masonry section of the contract specification, which referenced listed drawings depicting masonry work, including Drawing L-704.

As the work progressed, Colantonio directed Costa to furnish and install stone veneer on the masonry site walls, granite caps, and a cast stone entry sign. Costa said these site improvements were not included in the masonry work. The town had not solicited sub-bids for site improvement work because that was not one of the trades stipulated in the statute. The masonry specifications did not mention site improvements. Costa asked the town to issue a change order adding the site improvements to the masonry work, but the town refused.

Costa performed the disputed work under protest and sued the town and Colantonio for payment. The defendants responded that the site improvements were depicted on Drawing L-704, which was incorporated by reference into the masonry specifications. A trial judge granted declaratory judgment in favor of the town and judgment on the pleadings in favor of Colantonio. Costa appealed.

The Ruling

The Appeals Court of Massachusetts said the filed sub-bid statute defines trade work according to separate sections of the contract specifications. The work is also described by “number[ed] sheet[s] of plans” listed under each section of the specifications. The town and general contractor alleged that Drawing L-704, expressly referenced in the masonry specs, depicted the site improvements in question. Unfortunately, the drawing had not been entered into the record, and the appellate court did not have the drawing in front of it.

Without the drawing in the record, the court could not determine whether there was an error, latent or patent, in the masonry specifications with regard to the disputed site improvements. Without a determination of ambiguity in the contract documents, the court could not rule on whether Costa should be allowed to introduce evidence of trade custom. Consequently, the court vacated the judgments in favor of the town and Colantonio and remanded the matter to the trial court.

“By this remand, we do not suggest that this type of dispute cannot be resolved at the pleading stage. The problem here is with the record, not the law. Costa attached only some of the relevant bidding materials as exhibits to its complaint: i.e., the masonry specifications but not Drawing L-704 referenced therein.”

Conclusion

Out of necessity, specifications commonly incorporate drawings by reference. Ideally, drawings are segregated by trade, but not always. The question here is whether the site improvements were included in the masonry subcontractor’s scope of work or separate, in which case the general contractor should have hired a separate subcontractor to perform that work.

Practical Takeaway

The court provided some practical advice in its opinion: “Although Costa could have facilitated the more efficient resolution of this case by providing a full record in support of its complaint, it was not required to do so…. For their part, the defendants could have attached the missing materials to their motions but did not.”

Participants: No attorneys of record listed.
Before: Judges Neyman, Hershfang, and Toone
Opinion by: The full court.
Outcome: Judgments of trial court vacated; matter remanded

Source: Please click here to read the complete opinion.