Search
Logo
Construction Claims and Risk Management
Home
Explore
Explore

Past Issues

Browse previous newsletter issues

Case Summaries

Key case summaries and rulings

Practical Guidance

Risk assessment for contractors and construction managers

AI Basics

AI Tasks & Agents To Manage Risks

Owner's Corner

Explore past articles

Subscribe
About
Login
Construction Contract & Claims Management

Upcoming Live Events

9-Part Construction Claims Series
Includes 2026 ASCE 4th Edition Claims Book
Starts October 14, 2026


Pay-if-Paid and Pay-when-Paid Construction Clauses:
Who Bears the Risk of Non-Payment?
October 21, 2026


Certified Payroll / Davis-Bacon Series
Now features California Public Works Law and Davis-Bacon Related Acts
Starts October 29, 2026


CPM Schedule Training 2-Part Series
Includes 2025 Wiley CPM Book
Starts November 10, 2026


Implied Obligations in Construction Contracts:
What You Don’t Know Can Hurt You
November 17, 2026


Construction Scheduling: Games People Play - 2-part Series
Starts December 10, 2026

Jan 15, 2026

•

3 min read


Engineer’s Lack of Response Resulted in Owner Breach of Contract

Court of Appeals of Texas

Baker & Company Construction, LLC v. Smith County

Case no.: 12-24-00347-CV
Date filed: December 10, 2025

Overview

A Texas appellate court has ruled that a public project owner breached the contract when its consulting engineer failed to calculate, at the time of final acceptance, money owed the contractor for suspended work.

Background

Smith County awarded a contract to Baker & Company Construction LLC to widen and improve a road. Section 25 of the contract stated that in the event the county issued a stop work order, “such expense, as in the judgment of the ENGINEER is caused by such stopping of said work, shall be paid by the [county] to [Baker].” The contract defined the engineer as the Smith County engineer “or his authorized representatives, including consulting engineers.” The county had retained C. T. Brannon Corp. as the consulting engineer on the project.

At two points during the contract performance, Baker encountered utility infrastructure that obstructed the work. The first instance involved utility poles that had not been relocated in a timely manner. The second was a subsurface water main. In each case, the county ordered a work stoppage, for which Baker demobilized its workforce and equipment from the site, only remobilizing when the county had lifted the suspension. Baker notified the county and its engineer, Brannon, that Baker would seek additional compensation for the costs of the suspensions.

Baker completed the project, and the county issued final acceptance of Baker’s work. The contractor applied for final payment, including the increased costs caused by the suspensions. Section 51 of the contract governed final payment:

“Upon final acceptance of the completed work, the ENGINEER shall proceed to make final measurement and final statement of the value of all work performed and materials furnished under the terms of this agreement and provide to the [county], who shall pay to [Baker] on or before the 15th working day after the date of final acceptance the balance due to [Baker] under the terms of this agreement….”

Baker attempted to discuss suspension costs with Brannon, The engineer, however, never expressed an opinion on what, if anything, the contractor was owed for the suspensions. The county declined to include suspension costs in the final payment, and Baker sued for breach of contract, seeking payment of those costs.

The county asked the trial court to throw the case out. The Texas Local Government Code holds public project owners liable only for damages recoverable under the construction contract. The county argued Baker was seeking damages outside the contract. The trial court agreed, and Baker appealed.

The Ruling

The Court of Appeals of Texas said the contract had clearly called for compensation for government-ordered work stoppages. The amount was to be determined by “the judgment of the Engineer.” Upon the county’s final acceptance of the work, the engineer was required to calculate everything owed under the contract.

“The parties do not dispute that the Engineer accepted Baker’s completed work. Thus, in fulfilling his obligations to make the final measurement and statement of the value of all work performed and materials furnished under the contract, the Engineer was required to determine, in his judgment, the amount of the expenses Baker incurred which were caused by the two suspensions of work ordered by the County…. [O]nce the time for final payment to Baker passed and the Engineer had not made the necessary determination as to Baker’s incurred expenses under Section 25, the County was in breach of the agreement.”

The court rejected the county’s argument that because the contract left the matter to the judgment of the engineer, the county could not be held liable for the manner in which the engineer exercised that judgment.

“[T]he County maintained control to compel its Engineer to exercise such judgment when Baker made it known that it sought to recover such expenses. To conclude otherwise would mean that the Engineer simply could decline to make such a determination, thereby allowing the County to avoid its obligation to pay such expenses, if any, which are due and owing…. [W]e conclude that when the Engineer failed to meet this obligation under the contract, the County had an obligation to compel him to comply with the terms of Section 25 to avoid breach.”

Conclusion

The appeals court did not address the methodology for measuring the costs of the suspensions. This was left to the trial court upon remand.

Practical Takeaway

When a contract assigns responsibility for an exercise of judgment, doing nothing is not a viable option. This is true regardless of how contentious the task.

Case Details

Participants:
For Baker & Company Construction: Gregory Harwell
For Smith County: Nolan Smith

Before: Judges Worthen, Hoyle, and Davis

Opinion by: Judge Worthen

Outcome: Trial court order reversed; matter remanded

Source: Please click here to read the complete opinion.

Reply

Avatar

or to participate

Keep Reading

View more
caret-right

Subscribe to Our Newsletter

The latest news, articles, and resources, sent to your inbox weekly.

WPL Publishing Co., Inc.
PO Box 34215, Bethesda, MD 20827